What the Soakaway Calculator does
The soakaway calculator on this page will size a soakaway using the BRE Digest 365 method from your roof area and a measured soil infiltration rate. Fill in all 6 fields and the result updates as you type — there is no Calculate button to press and no page reload. It is most often used for sizing a soakaway for a new extension or outbuilding roof. We run a second free tools site as well — FreeToolsWorld.org.
How to use it
- Measure the roof or paved area draining to the soakaway, as a plan area.
- Get a design storm depth for your location and return period.
- Carry out a BRE 365 percolation test — three pits — and use the slowest infiltration rate.
- Enter the void ratio of your fill and read the excavation volume and plan size.
How it works
A soakaway is a void in the ground that accepts a storm's worth of water quickly and releases it into the soil slowly. Sizing it means two separate checks: the store must hold the design storm, and it must empty fast enough to be ready for the next one. BRE Digest 365 is the standard method in the UK and sets the second test as half-emptying within 24 hours.
The storage requirement is straightforward — the design rainfall depth over the contributing area, which for a 60 m² roof and a 30 mm storm is 1.8 m³ of water. What converts that into a hole size is the void ratio of whatever fills it. Modern plastic geocellular crates are about 95% void, so the excavation is barely larger than the water volume. Traditional granular stone fill is roughly 30% void, meaning you need over three times the excavation for the same storage — which is why crates have largely displaced rubble-filled pits.
The emptying check is where soakaways fail, and it rests entirely on the infiltration rate. That figure has to be measured, not guessed: BRE 365 specifies digging three trial pits, filling each to at least 75% depth, timing the fall from 75% to 25%, and using the slowest of the three results. A rate assumed from a soil description is the single most common reason a soakaway floods a garden, because the difference between a sandy loam and a silty clay is three orders of magnitude. Heavy clay may not percolate usefully at all, in which case a soakaway is the wrong solution and the water needs somewhere else to go.
Three practical constraints beyond the arithmetic. Building regulations in England and Wales require a soakaway to be at least 5 metres from any building and clear of the foundation influence zone, because saturating ground next to a footing is how subsidence starts. Surface water disposal commonly needs approval, and connecting it to a foul sewer is generally prohibited. And the design storm depth varies by location and by the return period you design for — the 30 mm default here is a rough 10-year, 6-hour figure for much of the UK, and your local value should come from a rainfall dataset rather than from a calculator default.
When to use it
- Sizing a soakaway for a new extension or outbuilding roof.
- Working out how many geocellular crates a job needs.
- Checking whether your soil percolates fast enough for a soakaway at all.
- Comparing crate storage against traditional stone fill.
Common mistakes to avoid
- Assuming an infiltration rate from the soil type instead of measuring it. The range spans three orders of magnitude.
- Using the 30% void ratio of stone fill and the excavation size of crates, or the reverse.
- Siting a soakaway within 5 m of a building, which risks saturating the ground beside the foundations.
Frequently asked questions
How big does a soakaway need to be?
Big enough to hold the design storm over the area draining to it, then divided by the void ratio of the fill. A 60 m² roof and a 30 mm storm needs 1.8 m³ of storage, which is about 1.9 m³ of excavation using 95% void crates or over 6 m³ using stone.
How do I measure the infiltration rate?
The BRE 365 percolation test: dig three trial pits, fill each to at least 75% of its depth, time how long the water takes to fall from 75% to 25%, and use the slowest of the three. Guessing from the soil description is the usual cause of failure.
How far from the house must a soakaway be?
At least 5 metres from any building under building regulations in England and Wales, and clear of the foundation influence zone. Saturating the ground next to a footing is a subsidence risk, and surface water disposal often needs approval in any case.